Today begins a 17-month-long commemoration of one of the great events in Seattle history. On July 4, 1917, the Lake Washington Ship Canal and Locks officially opened. It was the culmination of a multi-year project to connect Puget Sound to Lake Washington via Salmon Bay and Lake Union. I have written previously about this endeavor but would like to highlight one of the more significant, early construction milestones.
On February 2, 1916, fresh water from Salmon Bay entered the bigger of the two locks in the canal system. The lock was filled in 32 minutes with enough water so that it was equal to the level of Salmon Bay. As you can see from the second photo, there was enough pressure on the lock gate from Salmon Bay to push the gate open slightly. The February 3, 1916, Seattle Times called the event “the opening of the world’s greatest tidal basin.” (As you can see from the photo, snow covered the ground from one of the biggest snowstorms in Seattle history.)
After filling the locks, the Army Corps of Engineers opened the gates completely. This then became the route for tidal water to flow into Salmon Bay. At high tide, salt water would enter the bay and flood it. At low tide, water would drain out, exposing several acres of tide flats.
Prior to February 2, tidal salt water had entered Salmon Bay on the south side of the locks, where the present day spill gates are located. With the gates open, the Corps closed off the south side route and began to build the spill gate system, which is basically a dam helping to keep Salmon Bay at a constant level between 20 and 22 feet above sea level.
On February 3, the first boat, the Orcas, entered the locks and passed through to Salmon Bay. The locks would remain open until July 12, 1916, when the dam/spill gate was finished, and the Corps began to flood Salmon Bay with water from Lake Union. Salmon Bay would soon become the reservoir we now know.
The other day my mom asked me a very basic question and one that I had never considered. How exactly did they lower Lake Washington during construction of the Lake Washington Ship Canal and the Hiram M. Chittenden Locks? Completed in 1916 and officially opened in 1917, this was one of the great engineering feats of Seattle history.
In order to keep the canal system (it consisted of two canals, or cuts, one at Montlake and one at Fremont) at the same water level, Lake Washington (LW) had to lowered down to the level of Lake Union (LU). (See map above to see how Salmon Bay connected via the Fremont canal to LU and LU connected to LW via the Montlake canal.) This necessitated about a nine foot lowering, as LW was 29 feet above sea level and LU at 20 feet. The LW number is not exactly accurate because the lake level fluctuated by as much as eight feet during the year; it was highest in winter. In addition, Salmon Bay, which historically had been a tidal inlet—filling at high tide and mostly draining out low tide—had to be raised up to the level of LU.
In regard to my mom’s question, I had long known that it “took” three months to lower LW but didn’t know the details on how they did it. Here’s a timeline of how they lowered the lake and raised the bay.
July 12, 1916 – Locks closed in order to flood Salmon Bay and raise it to the level of Fremont canal and Lake Union. “Within thirty days the greatest fresh water harbor on the Pacific seaboard will be open to ocean-going ships entering Puget Sound,” reported the Seattle Times. This was a typical response to the opening of a fresh water port in Salmon Bay.
July 30, 1916 – Steamer F.G. Reeve first boat to pass through the locks, which opened the long desired passage from Salmon Bay through the Fremont canal to Lake Union, now all at the same water level. Reeve used the smaller of the two locks.
August 3, 1916 – Snag steamer Swinomish, under the command of Capt. F. A. Siegal, was the first boat to pass through the larger lock, “amid handclapping, cheers and the blowing of whistles,” wrote Thomas Francis Hunt in the Seattle Times. More than 2,500 people attended the opening. Next boat through was the Orcas. Both vessels did a quick spin in Salmon Bay before returning back to the locks.
August 25, 1916 – At 2 p.m., laborers used shovels to cut an opening into the cofferdam (temporary dam built to keep water out of the way) on the east side of Portage Bay. The plan was for the water to flow out of Lake Union and fill the Montlake canal. At the east end of the canal, or the very west side of Union Bay, were sluice gates, which would control the water flowing out of Lake Washington, still nine feet higher than Lake Union. An unknown skiff piloted by an anonymous man and two bare-headed boys was the first to run the canal.
“In exactly fifty six minutes the cut (Montlake canal) was filled to the level of Lake Union, and before the hour was up the current had ended and the eddies had ceased to foam. Logs torn from the cofferdam by the charging waters and hundreds of timbers and boards which covered the bottom of the cut floated to the surface…When the men with their shovels had broken the narrow neck of land, they sprang aside just in time to escape the inflow of water…In ten minutes the crowds on the cofferdam fled to escape being plunged into a raging torrent on the sides of the bank, which caved in in huge sections,” reported the Seattle Post-Intelligencer.
August 28, 1916 – Sluice gates in Lake Washington opened to allow water level in the lake to drop. Level was to be reduced about one and half feet in the first week with it dropping four feet by the end of September. Lowering Lake Washington down to the level of Lake Union did not occur until October.
By late October 1916 – Lake Washington and Lake Union and Salmon Bay are at the same level and boats can travel from Puget Sound to Lake Washington.
July 4, 1917 – Official opening of the locks and ship canal.