Putting Bertha in Perspective

So she’s not moving again. A few days ago Bertha’s barge got tippy, then on Tuesday, the ground near her started to give way and a massive sink hole appeared. Today, we have Governor Inslee putting out a cease and desist order, immediately stopping any further work by Bertha. The old gal cannot get a break.

I’d like to put this project in a bit of historical perspective. I am not apologizing for the slowdown but would like to point out that we have had a few projects that took more time.

Lake Washington Ship Canal and Locks – 63 years from conception to completion. Thomas Mercer was the first to propose a linkage between Lake Washington and Puget Sound via Lake Union, way back on July 4, 1854. The canal and locks officially opened on July 4, 1917. During the six decades it took to complete the project, there were federal reports, engineering reports, and naval reports. Attempts to dig the canal were made by lone individuals, speculators, Chinese work crews, and private corporations. And finally six different routes, including one through Beacon Hill, were proposed. Not until federal funding came through was the canal completed and it still took five years to complete the work.

Filling in the Duwamish River tideflats – At least 23 years. Seattle’s citizens had been dumping material in Elliott Bay since the upstart town’s earliest days but formal filling in of the tideflats didn’t start until July 29, 1895. In what was called the “greatest enterprise yet inaugurated in this city,” a dredge began to suck sediment out of one side of the tideflats and deposit it behind a barrier 2,000 feet away. By 1917, more than 90 percent of the tideflats had been filled, creating the monumentally unstable land of SODO and Harbor Island. Work had been stopped by lawsuits, the principal dredge company running out of money, and the occasional mechanical breakdown.

Denny Regrade – 33 years from first to last removal of sediment. It took five regrades to get rid of the great mound of Denny at the north end of downtown. The first was in 1897, followed by work in 1903, 1906, 1908-1911, and 1928-1930. There were workers who were electrocuted, who were attacked by children, who lost their arms, and who were crushed by landslides. A child taking a shortcut through the project died when dynamite being heated over an open flame exploded. Citizens sued the city and corporations. Corporations sued back. And, they even had problem with barges, which sank and ran into docks, shutting down the regrade. But on the plus side, they did find fossils from a mammoth, and they did complete the project.

So next time Bertha experiences a few delays, remember, she has a long way to go to break any record for most enduring Seattle project.

Material for for this story comes out of research I have done for my new book on Seattle – Too High and Too Steep: Reshaping Seattle’s Topography.

Seattle Technology Pt. 2 – The Self Dumping Barge

In my first technology post, I looked at the pile driver. I would now like to turn to an even less-heralded but rather fabulous piece of equipment, the self-dumping, reversible barge. They were critical to the final, 1928-1930, regrade of Denny Hill. Designed by naval architect William C. Nickum, the barges were used to tow dirt from the regrade out into Elliott Bay. Each cost $15,000 and was built by the Marine Construction Company. They were named the C.C. Croft and N.L. Johnson, after tugboat captains.

The barges were the same top and bottom with an open deck and two watertight chambers, or tanks, that extended the length of the barge between the decks. Each barge could carry about 400 cubic yards of dirt. To fill a barge, a tug nudged the barge under a chute built on a dock over Elliott Bay.

Filling barge Elliott Bay - May 1929
Filling barge Elliott Bay – May 1930

The tug then towed the loaded barge into the bay, where a crew member pulled a rope that opened a valve in one of the chambers. Within three minutes, water filled the tank, and the out-of-balance barge flipped over, dumping its load. No longer weighted down by the dirt, the barge rose high enough to drain the internal tank, which took about eight minutes. The tug returned the barge back to shore, ready for its next load.

Getting towed out into Elliott Bay
Getting towed out into Elliott Bay
Lopsided barge dumping its load into Elliott Bay May 1930
Lopsided barge dumping its load into Elliott Bay May 1930

The barges, or the barge workers, did not always perform as planned. In September 1929, one barge smashed its mate causing it to sink. Three weeks later, after both barges were repaired, workmen left the seacocks open on one, which caused it to flip and hit its tug, which promptly sank. And finally a week later, the remaining barge flipped while at dock, damaging the dock and scow, both of which were put out of service, forcing the entire regrade project to shut down for several days. Tug drivers also had the problem of the barges disappearing in foggy weather, which caused delays. Still the self-dumping, reversible barge was an amazing piece of early Seattle technology.

Oops, should have been a bit more careful
Oops, should have been a bit more careful

All images are from Seattle Municipal Archives.

Material for for this story comes out of research I have done for my new book on Seattle – Too High and Too Steep: Reshaping Seattle’s Topography.